Friday, March 11, 2011

March 11, 2011

Connected servo motors to the control board to begin servo tests.

Tuesday, March 8, 2011

March 8, 2011

Revised claw design with the mechanical engineer.

Friday, March 4, 2011

March 4, 2011

Adjusted coding to accomodate KEvin's new servo motor.

Wednesday, March 2, 2011

March 2, 2011

Found out that the gear system for the servos had been designed backwards and had to rebuild it.

Wednesday, February 23, 2011

February 23, 2011

Constructed poster for presentation. Recieved servos and relays for ROV.

Friday, February 11, 2011

February 11, 2011

Epoxied gears to pvc axels. Started work on poster for presentation.

Thursday, February 3, 2011

February 3, 2011

Submitted revised version of plan of procedures for review.